Watch Your Future Home Rise From The Sand

Time lapse update from July 2017:

Update from June 23, 2017:

Upwards we go! 17th Floor last week, 18th Floor next week. Only 2 more Floors, and then the Roof. Even with the recent inclement weather, we are making good progress thanks to our general contractor, Verdex Construction, and their seasoned construction team.

pompano beach condo new construction

Update from June 5, 2017:

The latest picture shown above, is of the west end of the 15th floor formed and awaiting concrete. The east end of the 16th floor is being formed and this half will be poured middle of next week. In the foreground, the personnel and material hoist, also known as the “buck hoist”, is being made ready for operation.

pompano beach condo new construction

Update from May 16, 2017:

The latest picture shown below, reflects the 12th floor under construction with concrete being poured. Framing of the interior walls is underway and as you can see from the picture above, the “crash barrier” walls on the second and third floor parking levels are under construction.

Pompano condos new

Update from May 1, 2017:

We are currently on schedule, forming and pouring a floor every 7-8 working days. As indicated in the photo below, the 10th floor has been completed. Interior unit framing for the residences starting on the 4th floor will begin in early May followed shortly by windows and sliding glass doors.

Time lapse update from March 2017:

sabbia beach progress construction update march 2017